Datteln

Germany  

A 2.7 MW ‘coal mine gas’ to energy project where besides electricity generation also a 2.2 MW heat extraction unit is operated.

A 2.7 MW ‘coal mine gas’ to energy project where besides electricity generation also a 2.2 MW heat extraction unit is operated. The valuable heat is fed into the heat grid and utilized by an major energy supplier and has been designed and commissioned by Green Gas Germany.
Some project characteristics:
• 2 x 1.4MW CHP plants
• Construction of CHP started and commissioned in 2007
• Construction of heat extraction started and commissioned in 2012
• Yearly electricity produced: approximately 18,000 MWh
• Yearly heat produced: approximately 15,000 MWh

Partner: Minegas GmbH
Start date: 2007
Activities: Project Development, Construction, Operation
Tech used: CHP
Type of gas: Coal Mine Gas
kWel: 2,716
Prospective annual emission
reduction in tons CO2 eq: 86,000

Lazy

Czech Republic  

Installation of two CHP units on the premises of active carboniferous mine Lazy.

Installation of two CHP units on the premises of active carboniferous mine Lazy. This installation is part of a large project of CHP units installation which Green Gas implemented in the area of Ostrava-Karviná district. For engines running we used mine gas drained thanks to the gas drainage station, which ensures the coal mining safety. In 2012 there was a change in the gas pipeline connection distributing the mine gas from abandoned mines. Electricity is delivered into local distribution network and heat is delivered into the boiler-room for heating purposes of the mine premises.

Some project´s characteristics:

  • Installed electrical output 2 x 1,6 MW
  • Put in the operation in 2008
  • Annual energy production: aprox. 24 000 MWh
  • Annual heat production: aprox. 12 000 MWh

Buttelborn

Germany  

Green Gas Germany operates the Landfill Gas to Energy project since 2000 in the Hessen area.

Green Gas Germany operates the Landfill Gas to Energy project since 2000 in the Hessen area. Currently Green Gas operates one engine with a capacity of 501 kWel and arranges the distribution and marketing of the electricity generated. Due to lowering gas quality and reducing gas quantities over the recent years, Green Gas has downscaled the project based upon availability of gas resources from 717 kWel at the start of the project to currently one CHP with a capacity of 501kWel to the satisfaction of client and project partners. Furthermore, with the installation of its patened low-methane-kit, Green Gas Germany is able to utilize landfill gas with methane contents of less than 35% CH4.

Customer: Abfall-Wirtschafts-Service GmbH, Büttelborn
Project name: Büttelborn
Region: Büttelborn (Hessen)
Partner: Riedwerke Kreis Groß-Gerau Start date: 2004
Activities: Project Development, Construction, Operation
Tech used: CHP Type of gas: Landfill Gas
kWel: 501
Prospectiv annual emission
reduction in tons CO2eq: 22,700

Jan Karel

Czech Republic  

Installation of two CHP units on the premises of active carboniferous mine ČSA.

Installation of two CHP units on the premises of active carboniferous mine ČSA. This installation is part of a large project of CHP units installation which Green Gas implemented in the area of Ostrava-Karviná district. For engines running we use gas from the central gas system delivering mine gas from active mines. Electricity is delivered into local distribution network and heat is delivered into the boiler-room for heating purposes of the mine premises.

Some project´s characteristics:

  • Installed electrical output 2 x 1,6 MW
  • First CHP unit put in the operation in 2009, second CHP in 2011
  • Annual energy production: aprox. 24 700 MWh
  • Annual heat production: aprox.7 400 MWh

Orlova

Czech Republic  

Installation of one CHP unit near the town square Orlová.

Installation of one CHP unit near the town square Orlová. This installation is part of a large project of CHP units installation which Green Gas implemented in the area of Ostrava-Karviná district. In this locality there was implemented a project to protect the area of Orlová town in face of coal mine methane spontaneous exit onto the surface which is not unfortunately a part of the project of CHP units installation. For engines running we use gas from the central gas system delivering mine gas from active mines. Electricity is delivered into the distribution network.

Some project´s characteristics:

  • Installed electrical output 0,8 MW
  • Put in the operation in 2007
  • Annual energy production: aprox. 5 400 MWh

Grube Siegfried

Germany  

Green Gas Germany runs the complete Landfill Gas to Energy project nearby Leipzig, Sachsen-Anhalt.

Green Gas Germany runs the complete Landfill Gas to Energy project nearby Leipzig, Sachsen-Anhalt; including drainage, compression and operation of the CHP since 2004. Furthermore, Green Gas Germany arranges the distribution and marketing of the electricity generated. Due to lowering gas quality and reducing gas quantities over the recent years, Green Gas has downscaled the project based upon availability of gas resources from 738kWel at the start of the project to currently one CHP with a capacity of 469kWel to the satifisfaction of client and project partners. In 2012 Green Gas revitalized the project by installing its patented low methane kit developed by Green Gas Germany, which resulted in a continuation of the 469 kW CHP and an increase in electrical output to the satifisfaction of all involved!
Customer: Westsächsische Entsorgungs- und Verwertungsgesellschaft mbH.

Project name: Grube Siegfried
Region: Trebnitz (Sachsen-Anhalt)
Partner: Mueg Mitteldeutsche
Umwelt- und Entsorgung GmbH Start date: 2004
Activities: Project Development, Construction, Operation
Tech used: CHP Type of gas: Landfill Gas
kWel: 469
Prospectiv annual emission
reduction in tons CO2eq: 23,000

Blumenthal

Germany  

4 MW installed CHP plant in the city of Recklinghausen, operated from closed mines with CH4 content below 25%.

4 MW installed CHP plant in the city of Recklinghausen, operated from closed mines with CH4 content below 25%.
Some project characteristics:
• 3 x 1.4MW CHP plants
• Construction of CHP started and commissioned in 2007
• Yearly electricity produced: approximately 25,000 MWh
Low-methane-kit installed
Partner: Minegas GmbH

Start date: 2007
Activities: Project Development, Construction, Operation
Tech used: CHP
Type of gas: Coal Mine Gas
kWel: 4,074
Prospective annual emission
reduction in tons CO2 eq: 129,000